Under Emre Özcan Engineering contract, within the scope of work “Yenice-Zonguldak Junction, Gokcebey Road, Survey and Engineering Design Services”, design construction documentation of 2 prestressed beam bridges have been prepared. Information about bridges as follows;

  • Tefen Bridge: 5 spans with a total length of 149.3 m
  • DDY Overpass Bridge: 3 spans with a total length of 74 m
Paylaş:
Project Details
Category Prestressed Bridges
Year 2017
Client Karayolları 15.Bölge Müdürlüğü